New Missionary House - Part 4
20 photos
-
7-24 Materials Stacked Under House to Dry
-
7-24 Walls Laid Out - Ready to Build
-
7-25 Back Porch Framed
-
7-28 Back Porch w Steps - Access to House
-
7-29 WT2 Walls Framed & Rough Electrical
-
7-31 WT2 Ceiling Panneling
-
7-31 WT2 Kitchen Cabinets w note from the Assembles
-
8-1 WT2 Back Porch Deck & Steps
-
8-2 WT2 Septic Tank Set & Drain Line
-
8-2 WT2 Trenches for Leach Bed
-
8-3 WT2 A Bathtub Set
-
8-3 WT2 Footer Being Poured around Septic Tank
-
8-3 WT2 Rough Plumbing
-
8-4 WT2 A Bedroom Panneled & Painted
-
8-4 WT2 Hallway Panneled & Painted w Back of Electrical Box in Hall Closet
-
8-5 WT2 First Kitchen Wall Cabinets
-
8-5 WT2 Master Bath & Shower
-
8-5 WT2 More Kitchen Cabinets
-
8-5 WT2 Plumbing for Main Bathtub & Shower
-
8-7 WT2 Water Tanks Set in Place