New Missionary House - Part 2
15 photos
-
WT-Day 1. Window Jambs
-
WT (Sun) 1st Container of Bldg Materials
-
WT (Sun) 2nd Conatiner of Bldg Materials
-
WT-Day 2. Start Trusses
-
WT-Day 2. Beams & Floor Joists on the bottom!
-
WT-Day 3. More Trusses
-
WT-Day 3. Srtip braces, Start Dbl 2x8 Beams
-
WT-Day 4. Finish Beams & Start Joists
-
WT-Day 4. Finish Scissor Trusses
-
WT-Day 5. Finish Joists, Start Decking
-
WT-Day 5. Last Trusses
-
WT-Day 6. Two Long Walls
-
WT-Day 6. Finish Decking
-
WT-Day 7. End Wall & 1st Truss
-
WT-Day 7. New Forks for the Tractor